Skip to content
gurn3k

BuildsWhose Move Is It · Snapshot

Whose Move Is It: Where Kubernetes pull requests wait

A TPM-style delivery analysis of kubernetes/kubernetes from public GitHub data: who has the next move on every open pull request.

Open live ↗Code on GitHub ↗

Role
Product owner
When
Oct 2026
Built with
Node · GitHub API · OpenRouter · Vercel
Status
Live research snapshot
Whose Move Is It report cover

01 · Situation

Kubernetes is one of the most active open-source projects, and its pull-request data is public. I wanted to find exactly where its PRs wait, and with which team.

02 · The call

Research showed that Kubernetes' own DevStats dashboards already measure parts of this. So I narrowed the project to the question they don't answer directly: whose move is it on each open PR? And I made the unit of analysis a team and a stage, never an individual person.

03 · What I did

  • Wrote a PRD, 10 decision records and 8 tickets.
  • Split every PR merged in the last 90 days into review stages (1,526 in the November snapshot), and put each open PR (1,367) in exactly one 'whose move' state: no response, reviewer, approver, merge, author or on hold.
  • Ranked team-and-stage queues by PR-days of waiting, and published a one-page report where every number opens the PRs behind it.
  • Had an LLM write a short risks brief from the code-computed facts. Code rejects any bullet that isn't cited, states a number not in the data, or makes a known misreading. Development took 7 paid runs for US$0.02 in total.
  • Set up automated checks that run the full test suite on every push and pull request, and made the README's figures come from the data, so the numbers and the guardrails can't quietly break or go stale.
  • Cross-checked my numbers against DevStats' own definitions, twice. The main finding agreed both times. The size of the medians didn't, and the write-up says what is and isn't known about the gap.

04 · Results

median wait for a reviewer's lgtm on a merged PR
2.9 days
median time from approval to merge
1.7 hours
of PRs waiting for a reviewer's lgtm sit with two teams (182 of 303)
60%
open PRs (22%) with no human response
295
of open PRs wait on a reviewer or approver (641 of 1,367)
47%

05 · Limits

One snapshot (November 21, 2026; the first was October 4), using labels as a proxy for whose move it is. No reviewer-capacity data and no users.

06 · What it shows

TECHNICAL PROGRAM MANAGEMENT · DELIVERY ANALYTICS · LLM GUARDRAILS · PRIVACY BY DESIGN